VA · electric · PUR-2026-00044

Appalachian Power — 2026 general rate case

Bottom line

The filing requests a 10.5% prospective ROE, compared with the 9.75% ROE authorized in Appalachian Power's prior biennial review. The statutory deadline is a backstop, not a scheduled decision date, and any revised rates cannot take effect before March 1, 2027.

Case summary

Appalachian Power filed its 2026 biennial base-rate review on May 29, 2026. The company requests approximately $61.4 million of additional annual retail generation and distribution revenue, including a $75.7 million distribution increase offset by a $14.3 million generation decrease. The SCC scheduled an October 20 evidentiary hearing; a final order is statutorily due by January 15, 2027.

Latest development
Order for notice and hearing entered

Jun 23, 2026

Next event
Public-witness hearing

Oct 19, 2026

Case stage

Regulatory process

hearing

  1. Filed

    May 29, 2026

  2. Testimony

    Not recorded

  3. Hearings

    Oct 20, 2026

  4. Briefing

    Not recorded

  5. Decision

    Jun 23, 2026

  6. Rates effective

    Not recorded

State rules

Base-rate reviews and adjustment mechanisms in Virginia

This docket is a full base-rate review. Selected charges can change on separate schedules without reopening every issue in this case.

Full base-rate review

Triennial review

The SCC reviews Phase I electric rates every three years under the statutory review framework.

Rate period: Three successive 12-month test periods ending before the review year.

Governing rule ↗

Between full reviews

Rate adjustment clauses

Project- and rider-specific

Virginia law permits separate rate adjustment clauses for approved generation, grid, environmental, and other investments. These riders operate independently from base rates and are reviewed in their own proceedings.

Governing source ↗

Fuel factor

Separate periodic filing

The fuel factor passes prudently incurred fuel and purchased-power costs through a separate SCC proceeding instead of waiting for the next base-rate review.

Governing source ↗
View the full Virginia regulatory framework →

Current case economics

Economics

Filed request and any outcome captured in this docket.

MetricUtility requestCurrent case outcomeLike-for-like difference
Annual revenue increase

$61.4M

Annual utility request

Not available

No outcome yet

Rate base

Not available

Not captured in current case sources

Not available

No outcome yet

Return on equity

10.5%

prospective common equity return · May 29, 2026

Not available

No outcome yet

Common equity ratio

Not available

Not captured in current case sources

Not available

No outcome yet

Residential bill impact

9.1

typical residential customer using 1,000 kWh per month · May 29, 2026

Not available

No outcome yet

Utility context

Prior authorizations, mechanism values, actuals, and company projections are shown separately because they are not default like-for-like case comparisons.

Common equity ratio

authorized · Appalachian Power Virginia retail authorized capital structure; 51.8% debt and 48.2% equity. · Mar 31, 2026

48.2%

Rate base

disclosed actual · Combined APCo and Wheeling Power rate-base proxy across Virginia, West Virginia, Tennessee, and FERC wholesale operations. · Dec 31, 2025

$14,215M

Return on equity

authorized · Appalachian Power Virginia retail authorized return on equity. · Mar 31, 2026

9.75%

Full docket record

6 events · 5 documents · 4 citations

View record
Last updated
Jul 20, 2026
Docket reviewed
Jul 20, 2026
Economics reviewed
Jul 20, 2026
Official documents
5
Evidence citations
4

Docket history

Material filings, hearings, orders, and effective dates.

  1. May 29, 2026

    Biennial base-rate application filed

    official commission · completed

  2. Jun 23, 2026

    Order for notice and hearing entered

    official commission · completed

  3. Oct 19, 2026

    Public-witness hearing

    official commission · scheduled

  4. Oct 20, 2026

    Evidentiary hearing

    official commission · scheduled

  5. Jan 15, 2027

    Statutory final-order deadline

    statutory deadline · scheduled

  6. Mar 1, 2027

    Earliest possible effective date for any revised rates

    statutory deadline · conditional

Documents

Docket and evidence documents linked to this proceeding.

Virginia SCC case information — PUR-2026-00044

official docket · direct ·

Open document ↗

SCC order for notice and hearing — hearing schedule

evidence · primary · Jun 23, 2026

Open document ↗

SCC order for notice and hearing — residential bill impact

evidence · primary · Jun 23, 2026

Open document ↗

SCC order for notice and hearing — requested economics

evidence · primary · Jun 23, 2026

Open document ↗

SCC order for notice and hearing — filing and statutory timing

evidence · primary · Jun 23, 2026

Open document ↗

Citations

Field-level excerpts and review metadata supporting material facts.

SCC order for notice and hearing — residential bill impact

commission order · Jun 23, 2026

SCC order for notice and hearing — requested economics

commission order · Jun 23, 2026

SCC order for notice and hearing — filing and statutory timing

commission order · Jun 23, 2026

SCC order for notice and hearing — hearing schedule

commission order · Jun 23, 2026

Raw observations

Stage-preserving economics and party positions as published in the canonical record.

MetricStagePartyPeriodValueEvidence
Residential monthly bill impactutility requestAppalachian Power Company — Virginia9.1
Revenue changeutility requestAppalachian Power Company — Virginia3.3%
Annual revenue changeutility requestAppalachian Power Company — Virginia$61.4M
Return on equityutility requestAppalachian Power Company — Virginia10.5%