MI · electric · U-21541

UMERC — 2024 general rate case

Closed case·Complete·Authorized

UMERCWEC Energy Group, Inc.Michigan Public Service CommissionOfficial docket not linkedVerified Jul 20, 2026 · 1 document · 1 citation

Bottom line

The first UMERC electric base-rate order since the utility began service reset capital terms and made the new rates effective January 1, 2025.

Case summary

The MPSC approved a settlement authorizing a $6.6 million increase for UMERC's non-mine electric customers, with a 9.86% ROE and 50% common-equity component.

Latest development
MPSC approved the UMERC rate-case settlement

Oct 10, 2024

Next event
No scheduled event

Not scheduled

Docket review
Jul 20, 2026
Economics review
Jul 20, 2026

Case stage

Regulatory process

complete

  1. Filed

    May 1, 2024

  2. Testimony

    Not recorded

  3. Hearings

    Not recorded

  4. Briefing

    Not recorded

  5. Decision

    Oct 10, 2024

  6. Rates effective

    Current stage

State rules

What Michigan reopens—and when

This docket is a full base-rate review. Selected charges can change on separate schedules without reopening every issue in this case.

Full base-rate review

No fixed recurring interval

A utility files when it seeks a base-rate change. The MPSC's general framework does not impose a common annual or multi-year filing cycle, but it requires a final Commission decision within 10 months of the application.

Rate period: Filing-specific forecast, historical support, and standard rate-case schedules.

Governing rule ↗

Between full reviews

Power and gas supply cost recovery

Variable surcharge · annual reconciliation

PSCR and GCR surcharges recover fuel, purchased power, transmission, and gas-supply costs above the amount in base rates. Actual costs are reconciled annually after a prudence review.

Governing source ↗

Investment Recovery Mechanism

Utility- and order-specific

An approved IRM can fund specified distribution investments between general rate cases. Collections and actual spending are reconciled under the terms of the utility's Commission order.

Governing source ↗
View the full Michigan regulatory framework →

Commission decision

Economics

Utility request and Commission-authorized outcome.

MetricUtility requestAuthorized outcomeLike-for-like difference
Annual revenue increase

Not available

Annual utility request

Not specified

Total company rate-case request or Commission-authorized outcome · Oct 10, 2024

Rate base

Not available

Not captured in current case sources

Not specified

The reviewed WEC post-order disclosure does not publish UMERC's total authorized electric rate base. · Jan 1, 2025

Return on equity

Not specified

Total company rate-case request or Commission-authorized outcome · Oct 10, 2024

9.86%

UMERC authorized electric return on equity under the U-21541 settlement order. · Jan 1, 2025

Not compared: scope differ

Common equity ratio

Not available

Not captured in current case sources

50%

UMERC authorized average common-equity component under the U-21541 settlement order. · Jan 1, 2025

Residential bill impact

Not available

Not captured in current case sources

Not available

Authorized value not captured

Full docket record

1 event · 1 document · 1 citation

View record

Docket history

Material filings, hearings, orders, and effective dates.

  1. Oct 10, 2024

    MPSC approved the UMERC rate-case settlement

    official commission · completed

Documents

Docket and evidence documents linked to this proceeding.

WEC Energy Group Form 10-Q reporting the UMERC U-21541 rate order

evidence · supporting · Sep 30, 2024

Open document ↗

Citations

Field-level excerpts and review metadata supporting material facts.

WEC Energy Group Form 10-Q reporting the UMERC U-21541 rate order

sec filing · Sep 30, 2024

Raw observations

Stage-preserving economics and party positions as published in the canonical record.

MetricStagePartyPeriodValueEvidence
Annual revenue changeauthorizedparty-commissionNot specified
Annual revenue changeutility requestUpper Michigan Energy Resources CorporationNot specified
Return on equityutility requestUpper Michigan Energy Resources CorporationNot specified
Common equity ratioauthorizedMichigan Public Service Commission50%
Rate baseauthorizedMichigan Public Service CommissionNot specified
Return on equityauthorizedMichigan Public Service Commission9.86%