VA · gas · PUR-2018-00080

Washington Gas Virginia — 2018 general rate case

Closed case·Complete·Authorized

Washington Gas VirginiaAltaGas Ltd.Virginia State Corporation CommissionOfficial docket not linkedVerified Jul 18, 2026 · 2 documents · 2 citations

Bottom line

The final order adopted Washington Gas's updated 53.48% common-equity capital structure and a 9.2% ROE while requiring refunds of excess interim collections.

Case summary

The Virginia SCC authorized a $13.2 million base-rate increase to incorporate costs associated with $101.9 million of prior SAVE investment and set a 9.2% ROE.

Latest development
Virginia SCC entered the Washington Gas final order

Dec 20, 2019

Next event
No scheduled event

Not scheduled

Docket review
Jul 18, 2026
Economics review
Jul 18, 2026

Case stage

Regulatory process

complete

  1. Filed

    Jul 31, 2018

  2. Testimony

    Not recorded

  3. Hearings

    Not recorded

  4. Briefing

    Not recorded

  5. Decision

    Dec 20, 2019

  6. Rates effective

    Current stage

State rules

What Virginia reopens—and when

This docket is a full base-rate review. Selected charges can change on separate schedules without reopening every issue in this case.

Full base-rate review

Application-based

Gas utilities file rate applications under the SCC's general rate-case rules rather than the Phase I and Phase II electric review schedule.

Rate period: Filing-specific schedules and supporting statements under the SCC rate-case rules.

Governing rule ↗

Between full reviews

No separate recurring mechanism is identified in the current state profile for this service.

View the full Virginia regulatory framework →

Commission decision

Economics

Utility request and Commission-authorized outcome.

MetricUtility requestAuthorized outcomeLike-for-like difference
Annual revenue increase

Not available

Not captured in current case sources

Not available

Authorized value not captured

Rate base

Not available

Not captured in current case sources

Not specified

The final order does not publish total authorized Virginia rate base; $101.9 million is identified only as SAVE investment incorporated into base rates. · Dec 20, 2019

Return on equity

Not available

Not captured in current case sources

9.2%

Washington Gas Virginia authorized return on common equity in PUR-2018-00080. · Dec 20, 2019

Common equity ratio

Not available

Not captured in current case sources

53.48%

Washington Gas updated five-quarter-average common-equity ratio adopted in PUR-2018-00080. · Dec 20, 2019

Residential bill impact

Not available

Not captured in current case sources

Not available

Authorized value not captured

Full docket record

1 event · 2 documents · 2 citations

View record

Docket history

Material filings, hearings, orders, and effective dates.

  1. Dec 20, 2019

    Virginia SCC entered the Washington Gas final order

    official commission · completed

Documents

Docket and evidence documents linked to this proceeding.

Virginia SCC final order in Washington Gas PUR-2018-00080

evidence · primary · Dec 20, 2019

Open document ↗

Virginia SCC Hearing Examiner report in Washington Gas PUR-2018-00080, part 2

evidence · supporting · Sep 16, 2019

Open document ↗

Citations

Field-level excerpts and review metadata supporting material facts.

Virginia SCC Hearing Examiner report in Washington Gas PUR-2018-00080, part 2

recommended decision · Sep 16, 2019

Virginia SCC final order in Washington Gas PUR-2018-00080

commission final order · Dec 20, 2019

Raw observations

Stage-preserving economics and party positions as published in the canonical record.

MetricStagePartyPeriodValueEvidence
Common equity ratioauthorizedVirginia State Corporation Commission53.48%
Rate baseauthorizedVirginia State Corporation CommissionNot specified
Return on equityauthorizedVirginia State Corporation Commission9.2%