PA · electric · R-2026-3060859

PECO Electric — 2026 general rate case

Bottom line

The requested increase was not litigated or authorized. The record preserves the withdrawn filing as material 2026 regulatory history for Exelon investors.

Case summary

PECO requested an approximately $429 million annual electric distribution revenue increase, then petitioned to withdraw the filing on April 16. The Commission granted the withdrawal and closed the docket on April 30, 2026.

Latest development
Commission granted withdrawal and closed docket

Apr 30, 2026

Next event
No scheduled event

Not scheduled

Case stage

Regulatory process

complete

  1. Filed

    Mar 30, 2026

  2. Testimony

    Not recorded

  3. Hearings

    Not recorded

  4. Briefing

    Not recorded

  5. Decision

    Not recorded

  6. Rates effective

    Not recorded

State rules

Base-rate reviews and adjustment mechanisms in Pennsylvania

This docket is a full base-rate review. Selected charges can change on separate schedules without reopening every issue in this case.

Full base-rate review

No fixed recurring interval

A utility initiates a general rate increase by filing a new tariff. It cannot file another general increase for the same service until the prior request is decided or its maximum suspension period expires.

Rate period: Case-specific; Pennsylvania law sets the filing and decision clock rather than a standard single-year or multi-year plan.

Governing rule ↗

Between full reviews

Distribution System Improvement Charge

Quarterly updates · annual reconciliation

An approved DSIC can recover eligible distribution investment between base-rate cases. The formula is updated quarterly and reconciled annually, subject to the utility's approved long-term infrastructure plan.

Governing source ↗
View the full Pennsylvania regulatory framework →

Current case economics

Economics

Filed request and any outcome captured in this docket.

MetricUtility requestCurrent case outcomeLike-for-like difference
Annual revenue increase

$429M

Annual utility request

Not available

Outcome not captured in current case sources

Rate base

Not available

Not captured in current case sources

Not available

Outcome not captured in current case sources

Return on equity

Not available

Not captured in current case sources

Not available

Outcome not captured in current case sources

Common equity ratio

Not available

Not captured in current case sources

Not available

Outcome not captured in current case sources

Residential bill impact

Not available

Not captured in current case sources

Not available

Outcome not captured in current case sources

Utility context

Prior authorizations, mechanism values, actuals, and company projections are shown separately because they are not default like-for-like case comparisons.

Annual revenue change

authorized · Prior authorized observation · Dec 12, 2024

$354M

Large Load Coverage Status

disclosed actual · PECO Electric large-load coverage · Jul 14, 2026

general_tariff_only

Large Load Coverage Summary

disclosed actual · PECO Electric large-load coverage · Jul 14, 2026

The reviewed current PECO Electric Tariff No. 8 includes general commercial and industrial rate schedules. It does not identify a separate dedicated large-load or data-center schedule.

Rate base

disclosed actual · Company-reported adjusted final rate base associated with the 2024 PECO Electric distribution proceeding; the settlement itself did not stipulate rate base · Dec 12, 2024

$8,855.6M

Full docket record

4 events · 3 documents · 4 citations

View record
Last updated
Jul 20, 2026
Docket reviewed
Jul 20, 2026
Economics reviewed
Jul 13, 2026
Official documents
3
Evidence citations
4

Docket history

Material filings, hearings, orders, and effective dates.

  1. Mar 30, 2026

    Electric distribution rate application filed

    official commission · completed

  2. Mar 31, 2026

    Rate increase filing posted by Commission

    official commission · completed

  3. Apr 16, 2026

    Petition to withdraw application filed

    official commission · completed

  4. Apr 30, 2026

    Commission granted withdrawal and closed docket

    official commission · completed

Documents

Docket and evidence documents linked to this proceeding.

PECO electric distribution rate case docket

official docket · primary ·

Open document ↗

Order granting PECO electric application withdrawal

evidence · primary · Apr 30, 2026

Open document ↗

PA PUC rate-filing discovery — R-2026-3060859

evidence · direct · Mar 31, 2026

Open document ↗

Citations

Field-level excerpts and review metadata supporting material facts.

PA PUC rate-filing discovery — R-2026-3060859

pa puc daily action search · Mar 31, 2026

Exelon Form 8-K reporting PECO rate-case withdrawals

sec filing · Apr 17, 2026

PECO electric distribution rate case docket

commission docket ·

Order granting PECO electric application withdrawal

commission order · Apr 30, 2026

Raw observations

Stage-preserving economics and party positions as published in the canonical record.

MetricStagePartyPeriodValueEvidence
Annual revenue changeutility requestparty-utility$429M
Revenue changeutility requestparty-utility11%