OH · Regulatory proceeding · 24-0508-EL-ATA

AEP Ohio Schedule DCT

Unknown proceeding·Order entered·Authorized

Public Utilities Commission of OhioOfficial docket not linkedVerified Jul 14, 2026 · 6 documents · 3 citations

Tariff application

Current position

Ohio has an implemented AEP Ohio tariff, but it is a utility-specific model rather than a statewide rule applying to every electric distribution company.

AEP Ohio's operating data-center tariff combines minimum-demand billing, a long service term, an exit payment, and a credit test that can require collateral covering half of minimum charges for the full contract term. Current state position: AEP Ohio data-center tariff approved and in use PUCO approved a settlement directing AEP Ohio to file data-center tariffs and lift its connection moratorium. AEP Ohio subsequently reported binding contracts under the tariff, confirming that the utility-specific framework is in operation.

Current stage
Order entered
Latest development
AEP Ohio Schedule DCT

Jul 23, 2025

Next event
No scheduled event

Not scheduled

Record type

Tariff application

Implementation

Final effective

Purpose

Track the proposed instrument, commission review, approval status, and effective terms.

Full docket record

2 events · 6 documents · 3 citations

View record

Docket history

Material filings, hearings, orders, and effective dates.

  1. Not scheduled

    Contracted-load conversion

    official commission · conditional

  2. Jul 23, 2025

    AEP Ohio Schedule DCT

    official commission · completed

Documents

Docket and evidence documents linked to this proceeding.

AEP Ohio reports contracts under its data-center tariff

evidence · direct · Feb 13, 2026

Open document ↗

AEP Ohio reports contracts under its data-center tariff

evidence · primary · Feb 13, 2026

Open document ↗

PUCO orders AEP Ohio to create data-center tariff

evidence · direct · Jul 9, 2025

Open document ↗

PUCO orders AEP Ohio to create data-center tariff

evidence · primary · Jul 9, 2025

Open document ↗

AEP Ohio Schedule DCT overview and current process

evidence · direct ·

Open document ↗

AEP Ohio Schedule DCT overview and current process

evidence · primary ·

Open document ↗

Citations

Field-level excerpts and review metadata supporting material facts.

AEP Ohio Schedule DCT overview and current process

utility webpage ·

AEP Ohio reports contracts under its data-center tariff

utility webpage · Feb 13, 2026

PUCO orders AEP Ohio to create data-center tariff

commission press release · Jul 9, 2025

Raw observations

Stage-preserving economics and party positions as published in the canonical record.

MetricStagePartyPeriodValueEvidence
Large Load Credit Collateralmechanism authorizedPublic Utilities Commission of Ohio50% of total minimum charges for the full contract term Collateral is waived only if the customer meets both the specified A-/A3 ratings and the liquidity test exceeding ten times the collateral requirement.
Large Load Eligibility Thresholdmechanism authorizedPublic Utilities Commission of OhioMore than 25 MW
Large Load Exit Feemechanism authorizedPublic Utilities Commission of Ohio36 months of minimum charges after year five The reviewed tariff summary permits termination after the fifth post-ramp contract year upon payment of the stated exit charge.
Large Load Generation Resource Costsmechanism authorizedPublic Utilities Commission of OhioNot identified in reviewed AEP Ohio sources
Large Load Infrastructure Cost Responsibilitymechanism authorizedPublic Utilities Commission of OhioTiered study fees; full upgrade security is project-specific
Large Load Minimum Contract Termmechanism authorizedPublic Utilities Commission of OhioLoad-ramp period plus 8 years
Large Load Minimum Paymentmechanism authorizedPublic Utilities Commission of Ohio85% above the first 25 MW · 100% above 75 MW The tariff uses a tiered formula rather than one flat percentage for the customer's full contract capacity.