MI · Regulatory proceeding · U-21990

DTE Electric 1,383 MW data-center special contracts

Unknown proceeding·Order entered·Authorized

Michigan Public Service CommissionOfficial docket not linkedVerified Jul 14, 2026 · 4 documents · 2 citations

Special contract

Current position

Michigan is developing through utility-specific terms and contracts, with Consumers already operating under approved provisions and DTE still moving toward a generally applicable tariff.

The MPSC conditionally approved project-specific supply and storage contracts with longer payment protection, early-termination charges, collateral, and customer-funded storage resources. Current state position: Consumers terms approved; DTE tariff follow-up ordered The MPSC approved Consumers Energy terms for data centers and other very large customers, including a 100 MW threshold, 15-year contract, and 80 percent minimum billing demand. It separately approved a DTE data-center contract with safeguards and directed DTE to file a large-load tariff.

Current stage
Order entered
Latest development
No completed event recorded

Not scheduled

Next event
No scheduled event

Not scheduled

Record type

Special contract

Implementation

Proposed

Purpose

Track the negotiated service arrangement, commission review, approval status, and effective terms.

Full docket record

1 event · 4 documents · 2 citations

View record

Docket history

Material filings, hearings, orders, and effective dates.

  1. Not scheduled

    DTE Electric 1,383 MW data-center special contracts

    official commission · completed

Documents

Docket and evidence documents linked to this proceeding.

MPSC explains Consumers and DTE data-center protections

evidence · direct · Jan 27, 2026

Open document ↗

MPSC explains Consumers and DTE data-center protections

evidence · primary · Jan 27, 2026

Open document ↗

MPSC approves DTE data-center contracts with conditions

evidence · direct · Dec 18, 2025

Open document ↗

MPSC approves DTE data-center contracts with conditions

evidence · primary · Dec 18, 2025

Open document ↗

Citations

Field-level excerpts and review metadata supporting material facts.

MPSC explains Consumers and DTE data-center protections

commission press release · Jan 27, 2026

MPSC approves DTE data-center contracts with conditions

commission press release · Dec 18, 2025

Raw observations

Stage-preserving economics and party positions as published in the canonical record.

MetricStagePartyPeriodValueEvidence
Large Load Credit Collateralmechanism authorizedMichigan Public Service CommissionUpfront collateral required · public summary does not quantify
Large Load Eligibility Thresholdmechanism authorizedMichigan Public Service Commission1,383 MW project-specific load
Large Load Exit Feemechanism authorizedMichigan Public Service CommissionUp to 10 years of minimum-demand charges
Large Load Generation Resource Costsmechanism authorizedMichigan Public Service CommissionCustomer fully funds approximately 1,400 MW of storage
Large Load Infrastructure Cost Responsibilitymechanism authorizedMichigan Public Service CommissionDTE bears service costs it cannot recover from the customer
Large Load Minimum Contract Termmechanism authorizedMichigan Public Service Commission19 years
Large Load Minimum Paymentmechanism authorizedMichigan Public Service Commission80% of contracted demand