Texas

Grid and interconnection rules

PUCT-approved ERCOT rules establish modeling and interconnection requirements for large loads, including visibility standards beginning at 25 MW. The newer Batch Zero process studies qualified projects of 75 MW or more together and is now moving through applicant classification and transmission planning.

Current position

ERCOT interconnection rules plus Batch Zero study process

Actions
1
Published tariffs
0
Legislation
1
Status
Adopted

Regulatory and utility record

Tariffs, contracts, and proceedings

Each record is shown on its own terms. A utility-specific tariff or contract does not automatically apply to every large customer in the state.

Statewide action · Rules effective; implementation ongoing

ERCOT large-load interconnection rules and Batch Zero

Texas is using grid-modeling, interconnection, and transmission-study rules rather than one statewide retail large-load tariff. Retail contract protections therefore cannot be inferred from the ERCOT framework.

Open proceeding

Why it matters

Texas is primarily a grid-access and transmission-planning story rather than a single retail tariff proceeding, so ERCOT implementation is the key tracker.

Enforceable terms

Key requirements

Eligibility threshold

25 MW visibility · 75 MW Batch Zero

Minimum payment

Not a retail-rate provision

Minimum contract term

Not a retail-contract provision

Service structure
ERCOT interconnection and operations rules, not a retail tariffEffectiveRetail contract, collateral, and minimum-payment terms remain utility- or customer-specific.
Charges and assessments
Transmission and interconnection upgrades identified through studyProject specificBatch Zero and related studies identify system work, but the ERCOT protocol does not establish one statewide retail take-or-pay charge.
Credit and collateral
Not established by the ERCOT rulesNot applicable
Exit protection
Not established by the ERCOT rulesNot applicable
Grid infrastructure
Batch study identifies transmission needsImplementation pendingBatch Zero evaluates system capacity and required transmission; it is not itself a statewide retail cost-recovery guarantee.
Generation and resource costs
Not established by the ERCOT grid rulesNot applicable
Capacity protection
Controllability, telemetry, and operational coordinationEffectiveCovered loads must satisfy ERCOT modeling and operational requirements so the grid operator can plan and respond reliably.
Reporting and true-up
25 MW visibility and study data requirementsEffectiveLarge loads provide forecasts, models, and status updates; higher-impact projects enter the applicable study process.

Official sources supporting these requirements

Statutory record

Legislation

1

SB 6

89th Regular Session

Large-load interconnection, operation, and cost rules

Requires Public Utility Commission and ERCOT standards for large-load interconnection, stranded-cost protection, reliability, colocated generation, demand management, and review of transmission-cost allocation.

Effective June 20, 2025.

Enacted

Directly related · Jun 20, 2025

Official bill

“Not specified” means the current official tariff record does not establish a normalized term. Retail tariff requirements are not inferred from wholesale-grid rules, interconnection processes, or pending policy proceedings.