Utility-specific tariff

Rockland Electric's effective SC7 tariff includes a High Voltage Distribution option originally approved to facilitate a 25 MW data center in Mahwah. It is a utility-specific delivery rate, not a statewide large-load framework.

Current position
Utility-specific precedent; no statewide model tariff
Policy status
Adopted
Implementation
1 effective tariff
Actions
1
Tariffs
1

Official actions

1

Rockland Electric

Rockland Electric 2025 base rate case

Effective

Rockland Electric initially requested approximately $18.74 million in additional annual revenue and later updated its request. The Board approved $15.25 million, effective July 1, 2026.

Open action

Utility instruments

New Jersey published tariffs

Only utility instruments with a published tariff record appear here. State policy and pending implementation remain in the framework above.

Service Classification No. 7 — High Voltage Distribution

Rockland Electric · NJ

effectiveauthorized · Effective Jul 1, 2026
Threshold1 MW
TermNot specified
Minimum payNot specified

“Not specified” means the current official tariff record does not establish a normalized term. Retail tariff requirements are not inferred from wholesale-grid rules, interconnection processes, or pending policy proceedings.