TX · gas · OS-23-00012594

T & L Gas — general rate case

Closed case·Complete·Utility request

T & L GasT & L GasRailroad Commission of TexasOfficial docket not linkedUpdated Jul 19, 2026View sources

Case summary

No case narrative is published.

Latest development
Commission entered the final order approving the settlement

Aug 22, 2023

Next event
No scheduled event

Not scheduled

Case stage

Regulatory process

complete

  1. Filed

    Not recorded

  2. Testimony

    Not recorded

  3. Hearings

    Not recorded

  4. Briefing

    Not recorded

  5. Decision

    Aug 22, 2023

  6. Rates effective

    Current stage

State rules

Base-rate reviews and adjustment mechanisms in Texas

This docket is a full base-rate review. Selected charges can change on separate schedules without reopening every issue in this case.

Full base-rate review

Annual adjustment · full case within five years

A gas utility using the interim infrastructure adjustment files annually and must complete a comprehensive cost-of-service rate case by the fifth anniversary of its first adjustment.

Rate period: The comprehensive case resets the investment, return, depreciation, tax, and allocation benchmarks used by later interim adjustments.

Governing rule ↗

Between full reviews

Interim Rate Adjustment / GRIP

Annual

A gas utility may update base rates for incremental infrastructure without a full cost-of-service package. Annual filings and earnings monitoring continue until the required comprehensive review.

Governing source ↗

Purchased gas adjustment

Tariff-specific pass-through

Purchased-gas clauses pass the commodity cost of gas through to customers separately from the utility's distribution base rates, with the calculation and update process set in the approved tariff.

Governing source ↗
View the full Texas regulatory framework →

Current case economics

Economics

Filed request and any outcome captured in this docket.

MetricUtility requestCurrent case outcomeLike-for-like difference
Annual revenue increase

Not available

Not captured in current case sources

Not available

Outcome not captured in current case sources

Rate base

Not available

Not captured in current case sources

Not available

Outcome not captured in current case sources

Return on equity

Not available

Not captured in current case sources

Not available

Outcome not captured in current case sources

Common equity ratio

Not available

Not captured in current case sources

Not available

Outcome not captured in current case sources

Residential bill impact

Not available

Not captured in current case sources

Not available

Outcome not captured in current case sources

Full docket record

1 event · 1 document · 2 citations

View record
Last updated
Jul 19, 2026
Docket reviewed
Jul 19, 2026
Economics reviewed
Jul 19, 2026
Official documents
1
Evidence citations
2

Docket history

Material filings, hearings, orders, and effective dates.

  1. Aug 22, 2023

    Commission entered the final order approving the settlement

    official commission · completed

Documents

Docket and evidence documents linked to this proceeding.

Railroad Commission final order in T & L Gas OS-23-00012594

evidence · direct · Aug 22, 2023

Open document ↗

Citations

Field-level excerpts and review metadata supporting material facts.

Railroad Commission final order in T & L Gas OS-23-00012594

commission final order · Aug 22, 2023

Railroad Commission final order in T & L Gas OS-23-00012594

commission final order · Aug 22, 2023

Raw observations

Stage-preserving economics and party positions as published in the canonical record.

MetricStagePartyPeriodValueEvidence
Common equity ratioauthorizedRailroad Commission of Texas55%
Rate baseauthorizedRailroad Commission of TexasNot specified
Return on equityauthorizedRailroad Commission of Texas9.5%