Case summary

No case narrative is published.

Latest development
Commission granted limited rehearing and amended the final order

Feb 19, 2025

Next event
No scheduled event

Not scheduled

Case stage

Regulatory process

complete

  1. Filed

    Not recorded

  2. Testimony

    Not recorded

  3. Hearings

    Not recorded

  4. Briefing

    Not recorded

  5. Decision

    Feb 19, 2025

  6. Rates effective

    Current stage

State rules

Base-rate reviews and adjustment mechanisms in Texas

This docket is a full base-rate review. Selected charges can change on separate schedules without reopening every issue in this case.

Full base-rate review

Annual adjustment · full case within five years

A gas utility using the interim infrastructure adjustment files annually and must complete a comprehensive cost-of-service rate case by the fifth anniversary of its first adjustment.

Rate period: The comprehensive case resets the investment, return, depreciation, tax, and allocation benchmarks used by later interim adjustments.

Governing rule ↗

Between full reviews

Interim Rate Adjustment / GRIP

Annual

A gas utility may update base rates for incremental infrastructure without a full cost-of-service package. Annual filings and earnings monitoring continue until the required comprehensive review.

Governing source ↗

Purchased gas adjustment

Tariff-specific pass-through

Purchased-gas clauses pass the commodity cost of gas through to customers separately from the utility's distribution base rates, with the calculation and update process set in the approved tariff.

Governing source ↗
View the full Texas regulatory framework →

Commission decision

Economics

Utility request and Commission-authorized outcome.

MetricUtility requestAuthorized outcomeLike-for-like difference
Annual revenue increase

$0.16M

Annual utility request

$0.14M

Commission-approved settlement annual revenue increase · Dec 17, 2024

Not compared: scope differ

Rate base

Not available

Not captured in current case sources

Not specified

The Rockin M Gas final order and limited rehearing order do not state total authorized rate base. · Mar 16, 2025

Return on equity

Not specified

Total company rate-case request or Commission-authorized outcome · Feb 19, 2025

Not specified

The Rockin M Gas final order and limited rehearing order do not state an authorized return on equity. · Mar 16, 2025

Not compared: scope differ

Common equity ratio

Not available

Not captured in current case sources

Not specified

The Rockin M Gas final order and limited rehearing order do not state an authorized common-equity ratio. · Mar 16, 2025

Residential bill impact

Not available

Not captured in current case sources

Not available

Authorized value not captured

Full docket record

1 event · 3 documents · 4 citations

View record
Last updated
Jul 21, 2026
Docket reviewed
Jul 21, 2026
Economics reviewed
Jul 21, 2026
Official documents
3
Evidence citations
4

Docket history

Material filings, hearings, orders, and effective dates.

  1. Feb 19, 2025

    Commission granted limited rehearing and amended the final order

    official commission · completed

Documents

Docket and evidence documents linked to this proceeding.

Railroad Commission order granting rehearing and amending the final order in Rockin M Gas OS-24-00017711

evidence · direct · Feb 19, 2025

Open document ↗

Railroad Commission final order in Rockin M Gas OS-24-00017711

evidence · direct · Dec 17, 2024

Open document ↗

Proposal for Decision in Rockin M Gas OS-24-00017711

evidence · direct · Nov 21, 2024

Open document ↗

Citations

Field-level excerpts and review metadata supporting material facts.

Railroad Commission final order in Rockin M Gas OS-24-00017711

commission final order · Dec 17, 2024

Railroad Commission order granting rehearing and amending the final order in Rockin M Gas OS-24-00017711

commission final order · Feb 19, 2025

Railroad Commission final order in Rockin M Gas OS-24-00017711

commission final order · Dec 17, 2024

Proposal for Decision in Rockin M Gas OS-24-00017711

recommended decision · Nov 21, 2024

Raw observations

Stage-preserving economics and party positions as published in the canonical record.

MetricStagePartyPeriodValueEvidence
Return on equityutility requestRockin M Gas CompanyNot specified
Annual revenue changeauthorizedparty-commission$0.14M
Annual revenue changeutility requestRockin M Gas Company$0.16M
Common equity ratioauthorizedRailroad Commission of TexasNot specified
Rate baseauthorizedRailroad Commission of TexasNot specified
Return on equityauthorizedRailroad Commission of TexasNot specified