FL · electric · 20260064-EI
Duke Energy Florida large-load tariff
Active proceeding·Filed·Utility request
Tariff application
Current position
The proposed 50 MW framework is not effective unless and until the FPSC approves it.
Duke filed revised large-load tariff and contract protections after withdrawing its earlier proposal.
- Current stage
- Filed
- Latest development
- Large-load tariff filed
- Next event
- No scheduled event
Apr 22, 2026
Not scheduled
Record type
Tariff application
Implementation
Proposed
Purpose
Proposed instrument, commission review, approval status, and effective terms.
Full docket record
1 event · 0 documents · 1 citation
View record
Full docket record
1 event · 0 documents · 1 citation
- Last updated
- Jul 22, 2026
- Docket reviewed
- Jul 22, 2026
- Economics reviewed
- Jul 22, 2026
- Official documents
- 0
- Evidence citations
- 1
Docket history
Material filings, hearings, orders, and effective dates.
Apr 22, 2026
Large-load tariff filed
official commission · completed
Documents
Docket and evidence documents linked to this proceeding.
No documents are linked to this proceeding.
Citations
Field-level excerpts and review metadata supporting material facts.
Duke Energy Florida large-load tariff petition
official record · Apr 22, 2026
Raw observations
Stage-preserving economics and party positions as published in the canonical record.
| Metric | Stage | Party | Period | Value | Evidence |
|---|